Lessons learned in commercial scale-up of new chemical processes (4)
Sequential vs. parallel engineering
Ideally,
all of the information needed to commit to a pilot plant, demo plant or
commercial plant is known when the decision is made. Sometimes, this is not the
case. Some part(s) of the process are not as well defined. However, pressures
caused by the market’s window of opportunity, fund
shortages or other factors make it necessary to commit to the start of design.
The risk
associated with this situation can be mitigated when prior art can be relied
upon to develop a design. More than one solution is often feasible, and each
solution must be developed, cost-estimated, technically assessed and
risk-ranked. The most common approach is to rank all options based on a team
assessment after one or more brainstorming sessions, and then develop and cost
out the first (or best team-assessed) option.
The
evaluation is ended if the first option is found to be technically and
economically feasible. If it is not, then the next option is assessed, and so
on. This process can be termed “sequential engineering.” The risk with the
sequential approach is extended time. In “parallel engineering,” more than one
option is examined concurrently, cost-estimated and technically assessed. The
risk with the parallel approach is waste of labor if the first option turns out
to be acceptable.
It is
important to remember that these activities are being performed while a task
force of tens to hundreds of engineers and designers are spending money developing design for
other parts of the process. The author favors the parallel approach, as it
limits the time to solution at a limited increase in engineering cost. Process
engineers with front-end engineering and design (FEED) experience are
comfortable with either approach. Unfortunately, other engineering disciplines
and project management often favor the
sequential approach, as they are asked to focus on one task at a time.
Backup option
Engineers
are often faced with choosing between multiple options, none of which can be
ruled out. As an example, multiple vendors may have equipment components that
appear to be technically suitable for a certain step in the process.
Unfortunately, very large quantities of material are needed to test each unit
on a continuous basis under actual conditions, which requires commitment to a
large-capacity, expensive demo plant.
This cost
may not be justifiable if the only reason is to produce the required quantity
of material for such a test. In this situation, it is feasible to select the
top two options, design the unit based on the first, and allow flexibility in
the design to replace the system with the second option. Obviously, this
process will require a shutdown and added costs. A team of experts and
engineers are used to select the top two options.
CONTINUES
Jazayeri, B., Reacxion http://www.hydrocarbonprocessing.com/magazine/2016/october-2016/process-control-and-instrumentation/lessons-learned-in-commercial-scale-up-of-new-chemical-processes
No comments:
Post a Comment