How Industrial Companies Can Get Better
at Design
Industrial companies are sometimes
perceived as lumbering giants that have difficulty responding to competitive
pressures and capitalizing on market trends. Product design cycles can last years,
even for incremental changes and upgrades to existing products. Targeted
redesign efforts—such as design-to-cost (DTC) initiatives, which set financial
objectives as the primary design constraint—suffer from the same long cycle
times. Meanwhile customer and market demands evolve much more quickly. Have
design processes always taken so long? What tools can companies apply when they
need to make rapid changes in product cost or design, to better respond to
customer demands or competitive threats?
A quick look to the past confirms
that industrial companies did not always have such long design cycles. In fact,
industrial and defense companies of yesteryear pulled off some incredible
design feats, without many of today’s supposedly accelerative technologies. Consider the following examples:
• The Supermarine Spitfire was the
main Royal Air Force fighter aircraft during World War II. Between 1936 and
1945, the aircraft changed engines, its loaded weight doubled, and its maximum
speed increased by 90 miles per hour. This rapid design evolution was only
possible due to an iterative design and testing approach.
• In the United States, the Saturn V rocket program started in 1961 with a seemingly impossible goal of putting a man on the moon by the end of the decade. To meet the timeline, its three stages and instrument unit were developed in parallel by four companies, each of which further compressed schedules by using parallel testing and development. Saturn V rockets were ready for use as part of the Apollo lunar missions just eight years later.
• Andrei Sakharov began designing the first Soviet thermonuclear device in 1949. After failing early performance tests, Sakharov and his team made two quick design iterations resulting in “Sakharaov’s Third Idea,” which led to a successful detonation in November 1955. The entire design cycle with three iterations was completed in only six years.
• In the United States, the Saturn V rocket program started in 1961 with a seemingly impossible goal of putting a man on the moon by the end of the decade. To meet the timeline, its three stages and instrument unit were developed in parallel by four companies, each of which further compressed schedules by using parallel testing and development. Saturn V rockets were ready for use as part of the Apollo lunar missions just eight years later.
• Andrei Sakharov began designing the first Soviet thermonuclear device in 1949. After failing early performance tests, Sakharov and his team made two quick design iterations resulting in “Sakharaov’s Third Idea,” which led to a successful detonation in November 1955. The entire design cycle with three iterations was completed in only six years.
People may argue that such speed was
possible due to enormous budgets and the sense of urgency imparted by war.
However, there are other examples where resources and urgency proved
insufficient. How did they do it? What can we learn from these efforts, and how
can we adapt and apply techniques used in other industries?
Two Approaches to Design
The successful programs noted above used an iterative design process known as “sprint and scrum” to accelerate progress—one that is used by software firms today—rather than a traditional, top-down waterfall design process. Waterfall development relies on tightly controlled project management and schedules to move the project through “design gates” until it’s ready for final release. There are a number of problems with this approach. Project management consumes time and resources, and the inevitable unforeseen risks trigger delays, with cascading problems for project schedules. Worse, it’s difficult to communicate progress to external stakeholders, because the design is not released until the last design gate. By that point, it’s frequently late and over budget.
The successful programs noted above used an iterative design process known as “sprint and scrum” to accelerate progress—one that is used by software firms today—rather than a traditional, top-down waterfall design process. Waterfall development relies on tightly controlled project management and schedules to move the project through “design gates” until it’s ready for final release. There are a number of problems with this approach. Project management consumes time and resources, and the inevitable unforeseen risks trigger delays, with cascading problems for project schedules. Worse, it’s difficult to communicate progress to external stakeholders, because the design is not released until the last design gate. By that point, it’s frequently late and over budget.
In contrast, an iterative,
sprint-and-scrum approach uses short design cycles to drive project progress.
The sprint phase is a period of concentrated individual or small team effort,
such as engineering or coding a module. At the end of each sprint, all
stakeholders come together for the scrum phase, where they review progress and
overall project status, and clarify goals for the next sprint period.
This approach enables faster cycle
times by revealing risks early on and minimizing project management overhead.
Equally important, it energizes staff by showcasing progress and fostering open
communication. The sprint-and-scrum approach is commonly used by software
companies, but until recently it hasn’t been applied to industrial design. We
think it should be, and we’ve seen firsthand how effectively it can accelerate
the design process and lead to better results.
Recently, we worked with a leading
light rail manufacturer that was under intense pressure to reduce its cost
base. The company had lost a series of high-profile project bids—primarily due
to the price of its equipment—and it had another bid due in just eight weeks.
It decided to launch a DTC effort to reduce costs by more than 10 percent in
time for the looming bid. With such a demanding time frame, management knew
that the existing design processes weren’t up to the task; it might take eight
weeks just to align the resources and set up the schedule! Clearly, the company
would need a different approach.
The solution was to employ a
sprint-and-scrum design method for the DTC effort. The working team divided the
light rail system into six sub-systems, and it created working design teams of
respected designers, engineers, and sourcing staff. During sprints, the teams
would redesign components or processes, or research supply options. The scrums,
which happened as frequently as every three days, provided a forum to bring
everyone together to collaboratively refine estimates and monitor progress.
During eight weeks of intense design
effort, the team implemented major changes, including redesigns to the car
frame, substituting internal and external cladding materials, and redesigning
the electrical harnessing. Changes also went beyond design, as the team
investigated ways to optimize manufacturing processes and improve sourcing
strategies. Due to the data-driven approach taken throughout the effort,
financial models provided the team with new insight into the cost drivers of
components, which were used to extract price concessions from key vendors.
Establishing a cross-functional team
broke down traditional silos and allowed engineering, sourcing, and
manufacturing leaders to see new perspectives and think differently about
solutions. The sprint-and-scrum methodology allowed the company to quickly
prioritize among many ideas and suggestions, weeding out those with low
potential and reallocating design resources on those with more promise.
When the dust settled, the team had
exceeded its goal and identified opportunities to reduce costs by 15 percent.
The company had begun implementing some of the easier and more straightforward
changes—in design, sourcing, and manufacturing—with the aim of reducing costs
for rail cars currently in production by as much as US$70,000 per unit.
So whether manufacturers are shooting for the moon or just looking for a way to quickly reset their product’s cost positioning, we believe the sprint-and-scrum approach will help them get there.
So whether manufacturers are shooting for the moon or just looking for a way to quickly reset their product’s cost positioning, we believe the sprint-and-scrum approach will help them get there.
http://www.strategy-business.com/blog/How-Industrial-Companies-Can-Get-Better-at-Design?gko=7e900
No comments:
Post a Comment